Hospital Hill Taumarunui

HOSPITAL HILL TAUMARUNUI

  • Client: DOWNERS / NZTA
  • Duration: 8 Months
  • Location: TAUMARUNUI – SH43

SCOPE:

MSC have undertaken physical construction works of 180LM long retaining wall on SH43. MSC have completed all physical works from sediment control planning and implementation, large earthworks, cut to fill, cut to waste, deep piling, timber structures, drainage and pavement construction. 

The wall construction consists of drilled holes between 4m and 12m deep, with casing of piles as required.  Significant cut to fill earthworks was undertaken to create the base platform, access tracks for both drilling and construction traffic. 

All works were supervised by MSC management team, consisting of Project Manager, Site Manager, Quality and Environmental Control Manager, and skilled labour.